the credibility of the supplier’s expedited Delivery Date, and whether the items can be at the workplace before the Scheduled Start Date. Note: If items for a Task must be expedited at additional cost, and the Planned Cost plus expediting cost is less than the approved Upper Cost Limit, then the expediting of the item does not need to be referred back to the approver of the Work Order. If the planning for the full Work Order is not yet complete (i.e. the Planned Cost is not yet finalised) the decision on whether to expedite should be referred back to the approver of the Work Order. Time This task shall be performed as soon as the critical issue with delivery is recognised. Resources Completion of this task is the accountability of the role nominated on the configured Resourcing flowchart.