Purpose To redirect work packages/Tasks that may require modification or cancellation to the Work Approval process for re-evaluation. Quantity One decision that modification or cancellation of a work package, or part of it, may be required. Quality If any change to work outcomes or stages are proposed as part of accepting the delay of all or part of a work the package/Task, it must return to the Work Approval process. If the proposed delay of the Scheduled Start Date for a part of the work package that is Work Scheduling System (WSS) generated may be longer than the trigger parameter for used by the WSS the work package must return to the Work Approval process. Time This task must be performed at least once per Schedule Period and at least one working day prior to the end of the Schedule Period. Resources Completion of this task is the accountability of the role nominated on the configured Scheduling flowchart.