Purpose To specify the changes to the schedule and work packages arising from the delay of some work beyond its Required Date. Quantity One agreed latest completion date for the delayed work. One specification of any changes to be made to work packages as a result of the delay. Quality The outcomes of this task shall be recorded on the same standard form used to record the acceptance of the risks of delaying work (as per Task Assignment SC.17 – Manager Accepts Risk) and filed for reference for a period of 12 months. The new latest completion date for Tasks shall be used to revise the schedule. Instructions for modifications to the work package shall be transmitted to the person accountable for the development of work package and Task specifications. Time This task must be performed at least once per Schedule Period and at least one working day prior to the end of the Schedule Period. Resources Completion of this task is the accountability of the role nominated on the configured Scheduling flowchart.