SET PRODUCTION STRATEGY Purpose: To specify the most cost effective way to operate the process.
Updated: 05/2019
No
Analyse & Improve AI.24 Implement Control Actions
IDENTIFY WHERE WE NEED TO FOCUS
IDENTIFY MOST COST EFFECTIVE STRATEGY
IMPLEMENT STRATEGY
Set Performance Targets ST.09 Define Constraints/ Opportunities ST.10 Lock in Targets, Strategies, OMS & Expenditures
Set Operating Master Schedule MS.01 Forecast Trigger Parameter Accumulation
PS.07 Estimate Output Distributions for Strategies (capability distributions)
PS.01 Analyse Target Performance Distributions
PS.09 Have Confidence Levels been met?
PS.04 Specify Strategy Objectives
PS.05 Identify Critical Process Work Steps
PS.06 Identify Potential Strategies
PS.08 Model Combined Strategy Effects
PS.10 Set Operating Specification Limits
Yes
Design Operating Time Operating Rate Feed Quality Product Quality
PS.02 Analyse Historic Performance Distributions
HOW IS THE STRATEGY EXECUTED
PS.03 Specify Production Process Work Steps (flowsheet)
PS.11 Identify Work Steps Completed & Controlled by Machines
PS.12 Specify Control System Outputs, Inputs, Specifications & Logic
Establish/ Programme Control System(s)
Set up Materials Management System(s)
PS.17 Specify Resource Service Levels
PS.15 Specify Manual Work Step Resources (labour, materials & equip’t)
PS.13 Identify Steps Completed or Controlled by People
PS.14 Specify Manual Work Steps, Triggers, Trigger Tolerances
PS.16 Group Work Steps for
Set up work packages in WSS
Efficient Work Management
Set Operating Master Schedule MS.02 Specify Activities for Scheduling Model
Copyright; McAlear Management Consultants 2004.