AAOM Handbook
RESOURCING: MATERIALS, TOOLS & SERVICES- Manage the Risks Purpose: To deliver the requirements for every work package to be completed at the scheduled time.
Updated: 09/2019
MANAGE RISKS
If Tasks do not need to be rescheduled continue monitoring resource availability
No
RE.19 Re-schedule Tasks?
Scheduling SC.03 Identify Synergies & Conflicts
Yes
DELIVER THE RESOURCES
RE.18 Reassign Resources
RE.21 Create or modify Tasks
RE.16 Obtain Resources
Yes
Yes
Yes
Scheduling SC.16
RE.17 Can Resources be Re-assigned from Another Scheduled Task?
Can Operations be changed to Reduce the risk?
RE.15 Can Resources be Obtained from Another Business Area?
RE.20 Can Work Scope be Split or Changed to Avoid Risk?
RE.22 Notify stakeholders of potential risk
No
No
No
Scheduling SC.11
Document critical issues & options
Copyright; McAlear Management Consultants 2004.