AAOM Handbook

Quality

In the case of discrete event (e.g. work order) Activities, the frequency of Activity occurrence should be the number of work packages executed in the measurement interval. This information should be derived from the work management system of record. In the case of 'continuous' Production Activities (e.g. crushing, grinding), the output should be the number of units of product processed in the measurement period. This information should be derived from the production system of record.

Time

At least once each reporting interval (typically monthly), but daily if practical.

Resources

Completion of this task is the accountability of the role nominated on the configured Operating Master Schedule flowchart.

© McAlear Management Consultants 2006

Operational Planning: Set Operating Master Schedule

Updated: August 2018

Page 46