WORK EXECUTION PROCESS- Recover the Schedule Purpose: To complete all allocated work, to specification, at the right time.

Updated: 05/2019

WE.10 Can Workplace Conditions be Established & Meet Outcomes?

WE.07 Can Resources be Obtained & Meet Outcomes?

WE.02 Can schedule be completed?

WE.13 Will the Task Specifications be Met?

RECOVER THE SCHEDULE

WE.23 Is extra time needed?

Yes

WE.24 Extra time approved?

No

No

Yes

WE.25 Are extra resources needed?

Yes

WE.27 Obtain resources

Yes

WE.26 Extra resources approved?

No

No

WE.34 Notify affected parties

Return to pre escalation point

WE.28 Can some Task(s) be rescheduled and still meet Required Date?