WORK EXECUTION PROCESS Purpose: To complete all allocated work, to specification, at the right time.

Updated: 08/2018

Resourcing RE.10 Move Resources to Work Location

Set Operating Master Schedule MS.16 Update Activity Frequency & Duration

DEAL WITH ADDITIONAL WORK

MONITOR SCHEDULE CONTEXT

WORK ASSIGNMENT

COMPLETE THE WORK

CLOSE OUT OF WORK

ASSESS CONDITIONS FOR SUCCESS

No

WE.09 Are Workplace Conditions Correct ?

WE.13 Will the Task Specifications be Met?

WE.17 Are all Task Requirements Complete?

Scheduling SC.15 Agree accepted schedule

WE.02 Can schedule be completed?

WE.04 Is the Task Understood?

WE.06 Are all Resources Available?

WE.14 Is Additional Work Required?

WE.19 Record all required data

WE.20 Return tools & surplus materials

WE.21 Close Task with all required data

WE.01 Review Schedule

WE.03 Assign Tasks

WE.12 Execute Task

Yes

Yes

Yes

Yes

Yes

No

Yes

Yes

No

WE.08 Obtain Required Resources

WE.11 Establish Required Workplace Conditions

Work Approva l WA.01 Raise Work Request (Non Urgent)

No

No

WE.22 Review work completion

WE.15 Can Additional Work be Completed

WE.05 Clarify Task Assignment

& Still Meet Outcomes?

No

WE.10 Can Workplace Conditions be Established & Meet Outcomes?

WE.07 Can Resources be Obtained & Meet Outcomes?

Yes

Yes

No

Yes

End

WE.18 Execute Additional Work

No

No

No

WE.16 Is Additional Work Urgent?

No

WE.23 Is extra time needed?

RECOVER THE SCHEDULE

Yes

Yes

No

WE.24 Extra time approved?

No

Work Approva l WA.01 Raise Work Request (Urgent)

No

WE.25 Are extra resources needed?

Yes

Yes

MANAGE URGENT WORK

No

WE.26 Extra resources approved?

WE.27 Obtain resources

WE.40 Cost above Threshold?

Yes

No

WE.28 Can some Task(s) be rescheduled and still meet Required Date?

Yes

WE.34 Notify affected parties

Return to pre escalation point

Yes

No

No

WE.29 Can some low impact Task(s) be rescheduled beyond Required Date?

WE.39 Impact above Threshold?

Yes

Scheduling SC.03 Identify Synergies & Conflicts between tasks

Yes

No

WE.37 Plan Work

WE.41 Notify manager

WE.30 Can the scope of some Task(s) be varied?

Yes

Yes

Yes

WE.33 Cancel Task

Work Approval WA.02 Is Work Urgent?

WE.38 Diagnosis Time above Threshold?

Yes

No

WE.35 Assign urgent work request

WE.36 Work Scope Defined?

No

WE.32 Is the work still required?

WE.31 Identify lowest risk Task(s) to reschedule

No

No

MANAGE RESCHEDULING TASKS